top of page
All Videos

All Videos

INSTALLATION: Video Player

GREENEDGE

PRE-INSTALLATION PREPARATION 

Drawings 1.jpg

DRAWINGS PREPARATION & PRODUCTION PLANNING

IMG_20180815_112345_edited.jpg

PRELIMINARY CLIENT BRIEFING 

IMG_20180813_100206_edited.jpg

INSTALLATION METHOD & REQUIREMENT BRIEFING

Upon receiving confirmation of order from the client, GreenEdge shall request a set of architectural and structural drawings for the purpose of producing GreenEdge Installation Shop Drawings and Sizing Tabulation.

Prior to the first delivery, GreenEdge technical personnel shall conduct a preliminary briefing to client and/or his project consultant, main contractor, sub-contractor (whichever is relevant) and wall installer (if applicable). This is to identify the key person at site; to determine the job scope of all related parties; to ensure the requirement of installation works are in line with our Installation Method Statement and Shop Drawings; to highlight the DOs & DON'Ts, etc.

Before the installation, the GreenEdge technical personnel shall coach the installer to ensure they fully understand and adhere to the correct method of installation and tools to be used. Coaching on planting of T10 starter bars before slab casting will also be conducted. During the coaching session any doubt raised by the installers will be clarified.

Working with Coffee

SITE DELIVERY COORDINATION

DSC02985_edited.jpg

PANELS PACKING & DELIVERY

IMG_20180802_085108_edited.jpg

UNLOADING THE PANELS

GreenEdge shall inform the client site representative the anticipated date of arrival of the GreenEdge panels in advance. It is for the client's earlier arrangement for a crane or similar to unload the panels from the trailer to the designated location. 

GreenEdge panels shall be packed and strapped in pallets. GreenEdge pallets are then to be loaded onto the trailer by using crane or forklift. The pallets can be stacked for a maximum of two layers, one above the other.

Upon arrival at site the GreenEdge panels are unloaded from the trailer using a crane or a forklift. Unloading platform & pallet jack / trolley are required for high-rise construction.

IMG_20180804_102936_edited.jpg

RECEIVING THE PANELS AT SITE

IMG_20180802_095637_edited.jpg

PANELS STORAGE AT SITE 

IMG_20180802_095602_edited.jpg

ADHESIVE MORTAR STORAGE AT SITE

The receiver of the GreenEdge panels must check and verify the quantity of panels delivered against the Delivery Order. Panels that found cracked or damaged, the receiver must clearly record the relevant information on the Delivery Order, in the presence of the trailer driver. The trailer driver is required to sign on the Delivery Order as acknowledgement of the defects. The Delivery Order is required to be stamped and signed by the client's representative as proof of the delivery.

The GreenEdge panels must be stored on a flat ground and must not be stacked for more than two layers. For high-rise buildings, the panels should be stored near to the crane hoisting area to avoid double handling / transferring.

GreenEdge Adhesive Mortar must be stored in a dry area and under a shelter or covered with water proof material. The shelf life of GreenEdge Adhesive Mortar is six months.

INSTALLATION: Products

GREENEDGE

INSTALLATION PROCESS

The installation of the GreenEdge partition wall element panels is up to six times faster than the use of traditional construction methods,

such as brickwork or laying block walls. When installing the panels, it is important to adhere to the local regulations and instructions,

and also to take the local special requirements and conditions into consideration.
“The installation of Acotec panels will result in a good outcome when our general instructions are followed"

INSTALLATION: Products
IMG_20180804_102052_edited.jpg

SITE PREPARATION

To identify the areas to install the GreenEdge panels.

To clean and mark the area by referring to the architectural drawing.

IMG_20180728_104524.jpg

DISTRIBUTION OF PANELS

Distribute GreenEdge panels to the areas where installation needs to take place by using pallet jack or trolley.

IMG_20180728_105248_edited.jpg

LIFTING & ERECTING OF PANELS

Unwrap the GreenEdge panels, lift them up, erect and arrange the panels accordingly.

6565f6b9-e221-4b98-80ab-edce0af25465.jpg

CUTTING OF PANELS

It is recommended to use an appropriate tools i.e. concrete cutter for any cutting on GreenEdge panels.

Adhesive 1.jpg

ADHESIVE MORTAR PREPARATION

To prepare GreenEdge Adhesive Mortar with a mixing ratio of 4 : 1. That is 4 parts of GreenEdge Adhesive Mortar to 1 part of water. Mix with an electrical mixer to achieve a homogeneous mix.

The pot life of GreenEdge Adhesive Mortar mixture is 30 minutes. Do not re-mix the dried mixture.

WhatsApp Image 2017-06-16 at 5.59.03 PM.

POSITIONING THE PANELS

To position the panels at the designated area and align it vertically and horizontally by using a crow bar and a spirit level.

WhatsApp Image 2017-06-13 at 4.37.34 PM_

INSTALLING THE PANELS

Always start the panels installation at a column or at an area where the panels will be intersected to form an “L” or “T” joint. Apply adequate GreenEdge Adhesive Mortar at all the structural members that will be connected to GreenEdge panel, such as column, slab & beam, next erect the panel and start to install. The marked/ painted side of the panel must always be installed at the bottom of the wall.

Wooden wedges 2.jpg

FIRMING THE PANEL POSITION

Hold the panel firmly by means of thrusting wooden wedges between the wall panel and the beam/slab soffit. These wooden wedges must be removed before finishing the installation works.

Ensure a gap of 20 - 50mm between the GreenEdge panel and the beam/slab soffit for GreenEdge Adhesive Mortar application.

WhatsApp Image 2017-06-10 at 5.07.12 PM_

SUBSEQUENT PANELS INSTALLATION

To install the subsequent panel, apply GreenEdge Adhesive Mortar to the groove of the previous panel and then interlock the tongue of the second panel into the groove of the previous panel.

IMG_20180816_093931.jpg

INSTALLATION OF LINTEL

For area where GreenEdge panel is used as lintel, prior to the installation, create an L-shape rebate of 100mm width at the adjacent panels at both side as supports for the lintel to sit on it. At place where the lintel is to be connected to a R.C. element, install an T10 steel bar as a support for the lintel. Both sides of lintel must be anchored with dowel bars to connect to the adjacent members.

IMG_20180821_112126.jpg

GREENEDGE PANELS FOR WINDOW & OTHER OPENINGS

Below the window, each panel must be anchored using U-bar (T10 Steel Bar) and a topping has to be casted over it in such a way that the two ends of the capping slots about 10mm into the sides of the panels by the side of the window.

In case of the gap between panels or panel and column which is lesser than 200mm, fill the gap with cast in-situ concrete.

IMG_20180914_150429.jpg

GREENEDGE STEEL BRACKET INSTALLATION

For the panel which is adjacent to R.C. column / wall, 2 nos. of 150mm T10 steel dowel bars (side) are required.


For external wall, GreenEdge steel bracket (Top) & 150mm T10 steel anti-slip bar (Bottom) is required for every panel. For internal wall, GreenEdge steel bracket (Top) & 150mm T10 steel anti-slip bar (Bottom) is required for every alternate panel.

WhatsApp Image 2017-07-08 at 10.42.21 AM

ANTI-SLIP BARS & DOWEL BARS INSTALLATION

To implant anti-slip bars and dowel bars, first drill a depth 50mm hole on the R.C member. Next, fill up the hole with grout and then insert the T10 steel bars.

WhatsApp Image 2017-07-08 at 10.42.29 AM

SEALING OF STARTER BARS & DOWEL BARS

After the panels are installed, patch up all the openings for starter bars and dowel bars with cement mortar.

MnE 1_edited.jpg

MECHANICAL & ELECTRICAL (M&E) OPENINGS

Proceed with the M&E works. All the openings for M&E must be created with electric cutter. Hacking with hammer and/or other inappropriate tools is prohibited.

IMG_20180914_151343_edited.jpg

PLUMBING & ELECTRICAL INSTALLATION

GreenEdge wall with hollows of 44mm diameter in the 75mm wall and 69mm diameter in the 100mm wall to allow the passage of water pipes, electrical wiring, HVAC and dydraulic installations without making holes/chases. 

WhatsApp Image 2017-06-13 at 4.37.40 PM_

FILLING OF GAPS BETWEEN PANELS

This is your Product Description. Write a short overview of the product including important features, pricing and any other relevant information for a potential buyer. Make sure your text is clear and easy to read. Tip from the pros: add an image or video of the product to give your clients a way of visualizing what you are selling.

IMG_20180827_152125.jpg

FIBER MESH INSTALLATION

Once the GreenEdge Adhesive Mortar is flushed at the gaps between panels, apply a layer of fiber mesh (100mm width) at all joints. Use GreenEdge Adhesive Mortar as the adhesive for the fiber mesh application.

Skim 1_edited.jpg

SKIM COATING

This is your Product Description. Write a short overview of the product including important features, pricing and any other relevant information for a potential buyer. Make sure your text is clear and easy to read. Tip from the pros: add an image or video of the product to give your clients a way of visualizing what you are selling.

INSTALLATION: Headliner
bottom of page